Water Service Line Replacement Phase 5

Project Manager: Gillie Lopez
Office Phone: (505) 891-5049
Contract Company: New Concepts, Inc.
Cost: $ 930,150.90
Stage: Construction
Schedule: April 2017 - September 2017
WaterServiceLineReplacement.jpg
The Water Service Line Replacement (WSLR) Project is for the replacing of existing polyethylene water service lines from the street to the water meter with new copper water service lines. The project will also replace Non-Automatic Reading Water Meters and Non-Standard Meter Boxes.

Additional Information:


  • Serviced Areas PDF. Please note that all polyethylene water service lines will be replaced in time, and that roads are being added to the list in order of severity with phases being added as budget allows.

Status Log:


  • March 2017: Phase 5 has been awarded to New Concepts Inc. Construction to begin in April 2017.

  • February 2017: Project will be sent out to bid this month.