G.O. Bond Road: Abrazo Road

Project Manager: Leila Momenzadeh
Office Phone: (505) 891-5048
E-Mail: lmomenzadeh@rrnm.gov
Contract Company: Wilson and Company
Cost: $  269,462.48
Stage: Design
Schedule: May 2018 - September 2018
Abrazo2
Final design and technical specifications to reconstruct Abrazo Road from Unser Boulevard to Chessman Drive, will include sidewalk, curb & gutter, Americans with Disabilities Act (ADA) compliant curb ramps, and street lighting as needed. The design will also include a new 8" water line to replace the existing water line as well as service lines to all platted lots along Abrazo Road from Unser Boulevard to Chessman Drive; and the design for a new 8" sewer line, manholes, stub outs to side streets, and sewer services to existing platted lots from Gemini Road to Encantado Ridge Court.

Additional Information:


Status Log:

  • September 2018: 90% Design plans are being reviewed and finalized.
  • August 2018: 60% Design plans were reviewed. 90% Design in process.
  • July 2018: 30% Design plans were reviewed. 60% Design in process.
  • June 2018: Design Process started.
  • May 2018:  Design Services was awarded to Wilson & Company. The kick-off meeting and field review was held on 5/30/18.