G.O. Bond Road: Country Club Drive

Project Manager: Kelly Heath
Office Phone: (505) 896-8242
E-Mail: kheath@rrnm.gov
Contract Company: Bohannan Huston, Inc.
Cost: $  193,722.00
Stage: Design
Schedule: May 2018 - September 2018
Country Club
The Country Club Drive Government Obligation (GO) Bond project, will include final design for reconstruction of Country Club Drive from the golf course entrance to Southern Boulevard SE. Improvements include new asphalt paving, sidewalk and curb & gutter replacement (as needed), and new Americans with Disabilities Act (ADA) compliant curb ramps. The design will also include a new water line to replace the existing water line along Country Club Drive.

Additional Information:


Status Log:

  • September 2018: 90% Design Plans were completed and are under review by City staff.
  • July 2018: 30% design plans were completed and reviewed; 60% will be completed later this month.
  • June 2018: The City selected Bohannan Huston, Inc. to complete the Final Design Plans for Country Club.
  • May 2018: Requests for Proposals (RFP) was advertised for Final Design. The City will review the Design Proposals and select an Engineering Firm to complete the design of this project.