G.O. Bond Road: Montreal Loop - Complete

Contract Company: TLC Plumbing and Utility
Cost: $  617,848.52
Stage: Complete
Final Completion: October 2, 2018
Montreal Loop  GO 2018
The reconstruction of Montreal Loop from Enchanted Hills Boulevard to Enchanted Hills Boulevard included replacement of non-compliant American with Disabilities Act (ADA) curb ramps as well as improvements to roadway pavement. Areas identified as having poor subgrade required the excavation of unsuitable material, replacement with suitable borrow, and subgrade preparation. The Contractor replaced broken curb and gutter (as identified in the plans), striping, and added collars for all utilities shown.