Lift Station 27, Force Main,  and Lift Station 16 upgrades

Project Manger: Stephanie DuBois
Office Phone: 505-896-8776
E-Mail: sdubois@rrnm.gov
Contract Company: AUI, Inc.
Cost: $  5,887,858.70
Stage: Construction
Schedule: July 2019 - April 2020
Lift Station 27 Site
Construct a new lift station to collect existing wastewater from Wastewater Treatment Plant 1 to transfer to Wastewater Treatment Plant 6 through a new force main that will run west on Sara Road, bore under NM 528 to Grande Court, south along old Grande Boulevard traveling west to 23rd Street where it will terminate into an existing manhole. The project will also include upgrades to lift station 16.

Additional Information:


Status Log:

  • March 2020: Construction is 100% complete with the installation of the force main. The new lift station is approximately 90% complete. The wet well and valve vault have been completed. Lift station 16 upgrades are approximately 80% complete.
  • December 2019: Construction is approximately 70% complete with the installation of the force main. The new lift station is approximately 10% complete with the wet well and odor control.
  • June 2019: The Notice To Proceed for AUI, Inc. is July 8, 2019.