Lift Station 27, Force Main,  and Lift Station 16 upgrades

Project Manger: Stephanie DuBois
Office Phone: 505-896-8776
E-Mail: sdubois@rrnm.gov
Contract Company: AUI, Inc.
Cost: $  5,852,591.61
Stage: Construction
Schedule: July 2019 - March 2020
Lift Station 27 Site
Construct a new lift station to collect existing wastewater from Wastewater Treatment Plant 1 to transfer to Wastewater Treatment Plant 6 through a new force main that will run west on Sara Road, bore under NM 528 to Grande Court, south along old Grande Boulevard traveling west to 23rd Street where it will terminate into an existing manhole. The project will also include upgrades to lift station 16.

Additional Information:


Status Log:

  • June 2019: The Notice To Proceed for AUI, Inc. is July 8, 2019.