King boulevard

Project Manager: Craig Hardy
Office Phone: (505) 891-5048
E-Mail: chardy@rrnm.gov
Contract Company: Albuquerque Asphalt Inc.
Cost: $  1,842,755.95
Stage: Construction
Schedule: November 2020 - May 2021
King Boulevard
The project includes curb ramp upgrades, miscellaneous sidewalk and curb and gutter replacements, replacement of the pavement surface, replacement of the multi-use path, and pavement marking. The current striping configuration of the roadway will be maintained. The western limits of this project are Rainbow Blvd, and the eastern limits are Wilpett Rd intersection.

Additional Information:


Status Log:

  • December 2020: Work on eastbound curb ramps has begun and the westbound multi-use path and pavement milling from Rainbow Boulevard to Wilpet Road is complete.
  • November 2020: Albuquerque Asphalt Inc. begins construction on November 18, 2020.