King Boulevard Expansion Project

Project Manager: Bill Ladd
Office Phone: (505) 891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt Inc.
Cost: $  8,055,618.24
Stage: Construction
Schedule: January 2023 - September 2023
IMG_0759

The King Boulevard Expansion project from Wilpett Drive to Unser Boulevard includes reconstructing and expanding King Boulevard from two lanes to four lanes, installing raised medians, curb and gutter, concrete sidewalk, concrete curb ramps which comply with the Americans with Disabilities Act (ADA), asphalt multi-use path, sanitary sewer main line and services, water line services, storm drain/detention pond modifications, intersection lighting, pavement markings, landscape gravel, and constructing a roundabout at the Wilpett Drive intersection.

Status Log:

  • January 3, 2023: Notice to Proceed.
057118 - Albuquerque Asphalt - King Blvd BT Unser Blvd and Wilpett Dr - EB WB Traffic Page_1
057118 - Albuquerque Asphalt - King Blvd BT Unser Blvd and Wilpett Dr - EB WB Traffic Page_2

The following restriction/detour route will go into effect on March 6, 2023 and last through mid-April 2023.

King Blvd Traffic Flow Version 2
2023_TrafficFlow_KingWilpett