This project includes the design, right of way acquisition, and construction of the Idalia Road Culvert Crossing at the Arroyo de la Barranca. The existing culvert pipes and headwall will be removed and replaced with a box culvert.
Funding for this project is from City funds (approximately $201,000) and federal funds (approximately $1,179,000).
Public Meeting
A virtual, public meeting was held on May 25, 2022 from 5:30pm - 6:30pm. To view the presentation slides, click or tap here.
Status Log:
February 2023: Continuing Environmental and Permit efforts
January 2023: Right of way maps approved
December 2022: First and second draft of Right of Way maps
November 2022: Working toward 90% Design and completing Right of Way maps