District 5

Project Manager: Bill Ladd
Office Phone: 505-891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt, Inc.
Cost: $ 674,839.52
Stage: Construction
Schedule: January 2023 - March 2023
Hybrid Mill

This is a Hybrid Mill & Inlay paving project that will replace the existing asphalt with new pavement and create an improved road base.  This is phase 1 of a project that is intended to address residential roadways throughout the community in need of maintenance beyond crack patch and sealing work.

Roads Start Date Estimated Completion Date
Grande Court - COMPLETED 1/3/2023 1/13/2023
May Circle 1/10/2023 1/25/2023
37th & 18th Avenues 1/19/2023 2/1/2023
DistrictFiveOverview