19th Avenue Reconstruction Project

Project Manager: Bill Ladd
Office Phone: (505) 891-85032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt, Inc.
Cost: $ 1,730,039.93
Stage: Construction
Schedule: January 16, 2023 - May 2023
19th ave

This project is for full roadway reconstruction between Golf Course Road and N.M. 528 with pond, ADA curb ramps, utility adjustments, and pedestrian push button improvements. 

Project Work Sequence:

Sequence 1 - January to February 2023: concrete work.

Sequence 2: January to March 2023: pond reclamation.

Sequence 3: February to May 2023: roadway rehabilitation.

*At times while project work is taking place, one-way traffic with posted detours will be in place.

Status Log:

  • January 16, 2023: Construction starting.