Quantum Rd. Reconstruction Project

Project Manager: Bill Ladd
Office Phone: (505) 891-5032
E-Mail: bladd@rrnm.gov
Contract Company: Albuquerque Asphalt
Cost: $ 3,786,569.43
Stage: Construction
Schedule: December 11, 2023 - June 2024
PW2251 Quantum Rd Reconstruction Project Web Page Picture

This project is for the full depth roadway reconstruction from Northern Blvd. to NM528 to include a new water line.  In addition, full depth reconstruction, to include new water lines on Laser Rd and Vortex Rd. 


Status Log:

  • December 2023:  Project starting