Rehabilitation of Trevino Dr, Player Loop, Fringe Ct, Player Ct, Wagon Train Dr and Parr Rd. The rehabilitation will consist of removal and replacement of asphalt pavement, 8" waterlines and services, curb and gutter removal and replacement as needed. San Juan de Rio and Antigua Rd will be roadway reconstruction only.
Beginning June 16, 2025
Work on Parr Rd, which will last for 60 days.
Beginning August 11, 2025
Work on Wagon Train Dr, which will last for 150 days.