Electrical Inspection

Temporary Pole Inspection

Confirm that the disconnect and receptacles are weatherproof and proper clearance at the point of attachment. In addition, check conductor capacity, fuses, switches and a check for GFCI for 15 and 20 amp receptacles.

Low Voltage Inspection

Check for integrity, markings on conductors, conductors are supported properly, conductors are kept 6’ away from attic access and no more than three (3) outlets per cable.

Rough In Inspection

When wires are run into the building and prior to being covered by finished walls, ceiling or floors, when the ground wires are made up to the boxes, the home runs are terminated in the panels, conduit work is secured (including boxes and nm cable).

Final Inspection

When the job is completed, a final inspection is required.