Idalia Road Corridor Study and Preliminary Design

Project Manager: Arnell Friedt
Office Phone: (505) 896-8242
E-Mail: afriedt@rrnm.gov
Contract Company: WHPacific, Inc.
Cost: $ 1,400,000
Stage: Preliminary Design
Schedule: July 2021 - July 2023
Idalia-Photo

This project includes the study and design of roadway improvements of Idalia Road from Northern Boulevard to Iris Road. The project is funded with City funds (approximately $200,000) and federal funds (approximately $1.2 million). This study will develop, evaluate, and refine alternatives for the corridor. Environmental documentation will be prepared in accordance with the National Environmental Policy Act (NEPA) and preliminary engineering plans will be developed.

Additional Information:

Status Log:

  • January 2022: Begin Development of Initial Alternatives
  • December 2021: Held First Public Meeting and Completion of Existing Conditions Analysis
  •  November 2021: Level C and D (initial) subsurface utility investigation
  • October 2021: Traffic Counts Analysis
  • September 2021: Geotechnical Investigation
  • August 2021: Topographical survey and aerial mapping
  • July 2021: Notice to Proceed given to WHPacific, Inc.