Idalia Road Improvements Project
| Project Manager: | Arnell Friedt |
|---|---|
| Office Phone: | (505) 896-8242 |
| E-Mail: | afriedt@rrnm.gov |
| Contract Company: | WHPacific, Inc. |
| Cost: | $ 3,200,000 |
This project includes the study and design of roadway improvements of Idalia Road from Northern Boulevard to Iris Road. This study will develop, evaluate, and refine alternatives for the corridor. Environmental documentation will be prepared in accordance with the National Environmental Policy Act (NEPA) and preliminary engineering plans will be developed. Final design will be completed for the first two phases including Priority Project 1 (Intersection of Idalia Rd and Broadmoor Blvd) and Priority Project 2 (Intersection of Idalia Rd and Loma Colorado Blvd). The project is funded with City funds (approximately $800,000), state funds (approximately $800,000), and federal funds (approximately $1.6 million).”
For Public Meeting
All current public meeting will post here. To see past meeting presentations, see the 'Additional Information' below.
Additional Information:
- Click or tap here Additional Information: for the presentation from the third public meeting held on December 11, 2024.
- Click or tap here Additional Information: Additional Information: for the presentation from the second public meeting held on May 4, 2022.
- Click or tap here Additional Information: Additional Information: for notes from the second public meeting held on May 4, 2022.
- Click or tap here Additional Information: Additional Information: Additional Information: Additional Information: for the project map.
- Click or tap here Additional Information: Additional Information: for the presentation from the first public meeting held on December 16, 2021.
- Click or tap here Additional Information: Additional Information: for the Public Meeting Summary from the first public meeting held on December 16, 2021.
Status Log:
- February 2026: Begin preparation of Right of Way maps for Priority Projects 1 and 2
- December 2025: Environmental Certification on-going
- November 2025: 90% Review Meeting held with NMDOT
- October 2025: 90% Design completed
- September 2025: Continuing Utility Coordination and Subsurface Utility Engineering
- August 2025: Ongoing Coordination with Utility owners
- June 2025: Additional Subsurface Utility Engineering (SUE)
- April 2025: Proceeding with 90% Design of Priority Projects 1 and 2
- March 2025: Additional Geotechnical Investigations
- December 2024: Public meeting
- November 2024: Proceeding with 90% Design of Priority Projects 1 and 2
- October 2024: 60% Design review meeting and Noise Study submitted
- September 2024: 60% Designs plans submitted
- June 2024: Continuing with 60% Design of Priority Projects 1 and 2
- May 2024: Kickoff meeting for Final Design of Priority Projects 1 and 2
- March 2024: Amendment for Final Design of Priority Projects 1 and 2 processed
- February 2024: Developing amendment for Final Design of Priority Projects 1 and 2
- January 2024: Capital Outlay funds added
- December 2023: Biological Report draft submitted
- November 2023: Final preliminary Drainage Report submitted
- October 2023: 30% Design complete
- September 2023: 30% Design review
- August 2023: 30% Design Plans submitted
- January 2023: Continuing with 30% design
- November 2022: Begin 30% design
- September 2022: Phase A/B Report Complete
- July 2022: Draft Phase A/B Report
- May 2022: Developing Phase A/B (Design Alternatives) Report
- April 2022: Continue Alternative Analysis and reach out to property owners located at the southwest corner of Idalia Rd and Iris Rd
- March 2022: Begin noise study
- February 2022: Pavement rating and pavement design reports complete; begin surveys for Biological and Cultural Resources
- January 2022: Begin Development of Initial Alternatives
- December 2021: Held First Public Meeting and Completion of Existing Conditions Analysis
- November 2021: Level C and D (initial) subsurface utility investigation
- October 2021: Traffic Counts Analysis
- September 2021: Geotechnical Investigation
- August 2021: Topographical survey and aerial mapping
- July 2021: Notice to Proceed given to WHPacific, Inc.